SVG ENGINEERING – CONSTRUCTION SUPERVISION CONSULTANT FOR FULIAN B1 FACTORY PROJECT – PHASE 5

12/11/2026 | 4 views

As part of the next expansion phase of the Fulian project, SVG Engineering continues to strengthen its reputation by earning the Client's trust in the construction packages for the B01 factory buildings. Undertaking two key responsibilities – Construction Project Management and Construction Supervision Consultancy – SVG Engineering is committed to maintaining stringent supervision standards throughout the construction site. This partnership not only helps optimize project operations and minimize technical risks but also ensures that the project is completed on schedule while meeting the highest quality standards.

CONSTRUCTION SUPERVISION AND PROJECT MANAGEMENT FOR FULIAN B1 FACTORY – PHASE 5, QUANG CHAU INDUSTRIAL PARK, BAC NINH, VIETNAM

- Investor: Precision Technology Component Co., Ltd.
- Address: Quang Chau Industrial Park - Bac Ninh Province - Viet Nam
- Construction Project: Construction of factory building B01 - Fulian
- Supervision Unit: Sao Viet Construction Design Consulting and Inspection Joint stock Company (SVG Engineering)
- Year of implementation: 2026

SCOPE OF CONSTRUCTION SUPERVISION AND PROJECT MANAGEMENT SERVICES FOR FULIAN B1 FACTORY – PHASE 5 AT QUANG CHAU INDUSTRIAL PARK, BAC NINH

A. Scope of Construction Supervision and Project Management Services Provided by SVG Engineering

For the construction of the B1 factory buildings under Fulian Phase 5 at Quang Chau Industrial Park, Bac Ninh Province, construction supervision and project management must be implemented in a coordinated and systematic manner to ensure effective control of all construction activities. These activities directly affect construction quality, project schedules, investment costs, and safety throughout the implementation process.

As the professional consulting unit, Sao Viet Construction Design and Inspection Joint Stock Company (SVG Engineering) undertakes inspection, monitoring, evaluation, and coordination activities within the scope of the signed contract. All activities are carried out based on approved design documents, technical requirements, contractual commitments, and relevant legal regulations.

1. Developing Project Management Strategies and Construction Supervision Plans

From the initial preparation stage, SVG Engineering develops construction supervision and project management plans based on the scale, technical characteristics, and implementation requirements of each factory building. The plans focus on key areas, including quality management, quantity control, schedule monitoring, occupational health and safety, environmental protection, and fire prevention and firefighting (FPF).

In addition to establishing an overall management plan, SVG Engineering provides consultancy on control procedures and coordination mechanisms among all parties involved in the project. These include material inspection procedures, construction quality supervision, quantity verification, work acceptance procedures, technical document management, and periodic reporting requirements.

Standardizing these procedures from the outset helps establish consistent working methods among the Client, contractors, and consulting unit, while providing a solid foundation for monitoring the entire project implementation process.

2. Assessing Contractor Capabilities and Construction Readiness

SVG Engineering reviews and evaluates the manpower, equipment, and professional capabilities of contractors participating in the construction project. The assessment focuses on technical personnel, construction management staff, machinery, specialized equipment, and the contractors' capacity to conduct testing and construction quality inspections.

At the same time, construction method statements proposed by contractors are reviewed to determine their compliance with approved designs, technical requirements, and actual site conditions. Solutions relating to occupational safety, risk control, and construction methods for technically complex work items are also assessed before implementation.

Through these assessments, SVG Engineering assists the Client in controlling contractors' construction readiness and minimizing shortcomings in resources and construction methods that could adversely affect the overall project performance.

3. Controlling Site Handover and Construction Site Organization

SVG Engineering monitors and coordinates the site handover process between the Client and contractors in accordance with the agreed schedule. Site conditions and facilities required for construction are inspected to ensure that construction activities can proceed in the correct sequence.

Throughout the construction period, the consulting unit regularly coordinates with relevant parties to resolve issues arising from site conditions, construction areas, and interfaces between different work items. The arrangement of working areas, coordination of construction teams, and management of cooperation among contractors are given particular attention to prevent conflicts during implementation.

Through continuous site monitoring, potential obstacles that could disrupt construction activities are identified and recorded, with appropriate solutions proposed to maintain coordination and consistency among all construction activities.

4. Reviewing, Verifying, and Managing Technical Documentation

Within the scope of its assigned responsibilities, SVG Engineering reviews technical documents, submission dossiers, and construction method statements prepared by contractors before they are submitted to the Client for consideration and approval.

The review focuses on the consistency of these documents with approved design drawings, contractual requirements, technical standards, and actual project conditions.

Where documents are incomplete or fail to meet the required standards, the consulting unit provides professional comments and recommendations for contractors to supplement or revise them in accordance with the agreed procedures.

If any inconsistencies or inadequacies are identified in the design documentation, SVG Engineering promptly notifies the Client, analyzes potential impacts, and proposes appropriate solutions.

Technical document control is carried out regularly to minimize discrepancies between the design and actual construction conditions, while reducing the risk of unplanned additional work.

5. Supervising the Quality of Materials, Equipment, and Construction Works

Quality control of construction materials and products is one of the key responsibilities of SVG Engineering's construction supervision services.

Before being used on site, materials, structural components, and construction equipment are inspected through their origin documentation, quality certificates, test results, and other relevant technical documents.

During construction, the consulting unit continues to monitor the delivery, storage, preservation, and use of materials and equipment at the construction site. Construction activities are inspected at each stage and checked against approved design drawings, technical specifications, and quality requirements.

In addition, test results for materials, structural components, and construction products are reviewed and evaluated as a basis for quality control and acceptance procedures.

Depending on the nature of the work and the project's requirements, SVG Engineering coordinates the implementation of verification testing or quality assessments for relevant structural elements and construction items in accordance with applicable regulations.

6. Monitoring Construction Progress and Managing Construction Quantities

SVG Engineering regularly updates construction progress in each area and for each work item of the B01 factory buildings, comparing actual site performance with the overall schedule agreed upon by the Client.

Based on the implementation plan, the consulting unit monitors contractors' mobilization of manpower and equipment, as well as their construction arrangements. Contractors are required to prepare detailed construction schedules, allocate appropriate personnel, and ensure sufficient resources to meet their committed milestones.

When potential delays or factors that may disrupt construction activities are identified, SVG Engineering analyzes the causes and recommends appropriate corrective measures.

Schedule adjustments are considered based on actual site conditions to ensure coordination between different work items and minimize any impact on the project's completion date.

Alongside schedule management, construction quantity inspections are conducted by reviewing documentation, inspecting actual site conditions, and evaluating the completion status of individual work items.

These activities provide a basis for verifying completed quantities, supporting construction acceptance procedures, and managing construction costs within the scope of the assigned responsibilities.

7. Monitoring Compliance with Occupational Safety, Environmental Protection, and Fire Prevention and Fighting Requirements

Throughout the construction period, SVG Engineering places particular emphasis on inspecting compliance with occupational health and safety regulations, environmental sanitation requirements, and fire prevention and firefighting regulations at the construction site.

Measures to prevent accidents, the provision of personal protective equipment (PPE), construction area arrangements, and the control of potential safety hazards are regularly monitored.

For work items involving specialized technical requirements or higher levels of risk, the consulting unit inspects the implementation of approved protective measures and supervises safety conditions for workers and adjacent structures. Structural monitoring activities are also monitored whenever required by the project.

If construction conditions fail to meet safety requirements or show signs of potentially affecting construction quality, SVG Engineering promptly issues notifications, recommends corrective measures, and exercises its authority to request a suspension of construction when necessary, in accordance with its assigned responsibilities, contractual provisions, and applicable regulations.

8. Managing Construction Site Diaries, Reports, and Risk Control

SVG Engineering maintains construction supervision diaries throughout the performance of its assigned duties to record construction activities, inspection results, outstanding issues, and corrective actions taken on site.

In addition to maintaining supervision records, the consulting unit receives and reviews contractors' reports, consolidating information on construction quality, quantities, progress, and resource utilization.

Important matters are reported to the Client periodically or whenever issues requiring timely resolution arise.

Risk management is implemented through the identification and assessment of factors that may affect the construction investment and implementation process, such as design changes, additional work quantities, schedule delays, technical errors, and potential safety hazards.

Based on its monitoring results, SVG Engineering provides professional assessments and appropriate recommendations, supporting the Client in evaluating solutions, adjusting implementation plans, and effectively controlling the overall project execution process.

9. Inspecting Construction Works for Acceptance and Finalizing Quality Documentation

SVG Engineering coordinates with the Client and contractors to organize inspections and acceptance procedures for construction works, construction stages, structural components, and completed works in accordance with applicable regulations.

Before each acceptance inspection, relevant documents are reviewed, including inspection records, test results, material certificates, technical documentation, and other necessary quality-related requirements.

Any work that fails to meet the required standards is recorded, and contractors are requested to carry out corrective actions and repairs before acceptance is reconsidered in accordance with the established procedures.

For as-built documentation, the consulting unit conducts reviews in accordance with the construction acceptance procedures, provides verification within the scope of its assigned responsibilities, and coordinates with the Client in preparing documents and participating in explanations when competent state authorities conduct inspections of construction acceptance activities.

10. Coordinating Handover and Transfer for Facility Operation

Once construction items have been completed and meet the handover requirements, SVG Engineering coordinates with the Client, contractors, and receiving parties to monitor the facility handover process.

Completion documents, as-built drawings, quality records, technical operation manuals, and other information necessary for facility management and operation are inspected, consolidated, and archived in accordance with applicable regulations.

In addition, the consulting unit monitors contractors' fulfillment of their responsibilities regarding operational guidance, personnel training, and technology transfer within the scope of their contracts.

These activities help the Client receive complete documentation, understand the operating principles of the systems, and prepare all necessary conditions before the facility is officially put into operation.

B. Documentation and Deliverables of Construction Supervision and Project Management Services

During the implementation of construction supervision and project management services for Fulian B01 Factory – Phase 5, SVG Engineering prepares, reviews, and consolidates professional documentation to support the Client's project management activities.

Documentation and service deliverables are developed in accordance with the project schedule, contractual requirements, and the consulting unit's assigned responsibilities, including:

  • Project Management and Construction Supervision Plans: Documents outlining the implementation strategy, construction supervision plans, quality inspection procedures, schedule and quantity control measures, and other relevant management activities.

  • Construction Supervision and Progress Reports: Reports consolidating construction activities on a daily, weekly, monthly, or as-requested basis. These reports cover completed quantities, work quality, progress of individual construction items, outstanding issues, and proposed corrective measures.

  • Inspection Records and Construction Acceptance Documentation: Documents recording inspection results, acceptance of construction works, acceptance of construction stages, and acceptance of structural components in accordance with applicable regulations.

  • Documentation for Completion Acceptance: Consolidated inspection results, quality assessments, and reviews of acceptance documentation to assist the Client in completing the necessary procedures before the facility is put into operation.

  • Specialized and Incident Reports: Technical information, professional assessments, and recommendations for resolving unexpected issues or matters requested by the Client during project implementation.

  • Technical Management Records and Related Documentation: Including construction supervision diaries, quality inspection documents, progress monitoring records, quantity tracking documents, and other professional records within the scope of the services.

  • Documentation for Coordination with Regulatory Authorities: Participation in the preparation, review, and provision of necessary documents when the Client works with state management authorities regarding construction acceptance inspections.

  • Other Contractual Deliverables and Professional Obligations: Fulfillment of all other tasks, reporting requirements, and professional responsibilities agreed upon by the parties in the consultancy service contract.

The entire documentation system is managed and updated throughout the project implementation process, ensuring continuity of information, providing a reliable basis for inspection and verification, and supporting effective project management.

PROJECT PHOTOS: SVG ENGINEERING PROVIDING CONSTRUCTION SUPERVISION AND PROJECT MANAGEMENT SERVICES FOR FULIAN B1 FACTORY – PHASE 5 AT QUANG CHAU INDUSTRIAL PARK, BAC NINH

COST OF CONSTRUCTION SUPERVISION CONSULTANCY AND PROJECT MANAGEMENT FOR FACTORY BUILDING

Please immediately contact Hotline: 0902.593.686 (Mr. Thang) & Email: svg.engineer@gmail.com for support and advice on issues related to Construction Supervision Consulting and Project Management for Factory Building in Viet Nam ... Best regards! 


VietNam construction consulting - Mr. Thang 0902.593.686

CONTACT US:

SAO VIET CONSTRUCTION DESIGN CONSULTING AND INSPECTION JOINT STOCK COMPANY

🏢 Hai Phong Office :

Address : 7th floor SVG Building - Bui Vien Street - An Bien Ward - Hai Phong City
☎ Tel: (0225) 3.747.819
📞 Hotline: 0902.593.686
📧 Email: svg.engineer@gmail.com

🌎 VietNam Website: giamsatcongtrinh.com 
🌎 English Website: en.giamsatcongtrinh.com
🌎 China Website: cn.giamsatcongtrinh.com

 Youtube Channel: https://www.youtube.com/@svgengineering

🏢 Representative offices:

  • Ha Noi  Branch Office : No. 9/ 81 Hoang Cau Street, Dong Da Ward, Hanoi Capital
  • Ho Chi Minh Branch Office: 2/1C Cao Thang Street, Ban Co Ward, Ho Chi Minh City
  • Hue Branch Office : M25 Lot , 21 Street, Dong Nam Thuy An, Thanh Thuy Ward, Hue City