CONSTRUCTION SUPERVISION AND COMPLETE ACCEPTANCE OF TONGWEI FACTORY PROJECT PHASE 1 IN VIETNAM

20/8/2024 | 145 views

The finishing work of the factory is the last step of the construction work, so the order of finishing work needs to be considered and calculated so that during the entire factory construction process, there is no remaining work, otherwise causes damage to the finished place. The process of carrying out factory construction work is often intertwined, so it happens that the following things damage or hinder each other, so the quality supervision consulting engineer next to the investor is the one who has to organize coordination. The members participate in the construction in a smooth and harmonious manner, without affecting each other's work between the units that have to construct on the same construction site. To achieve harmony and harmony in the process of completing the factory, the consulting and supervising engineer must come up with a coordination plan in the coordination schedule (master schedule) and discuss with relevant parties to Do it together, avoid prolonging construction time and wasting effort such as doing it over and over again due to lack of coordination.

CONSTRUCTION SUPERVISION AND COMPLETE ACCEPTANCE OF TONGWEI FACTORY PROJECT PHASE 1 IN VIETNAM

- Investor: Tongwei Electronics Vietnam Co., Ltd
- Address: An Duong Industrial Park - Hai Phong City
- Construction Project: Industrial factory of Tongwei Electronics (Vietnam) Co., Ltd. Phase 1
- Supervision Unit: Sao Viet Design Consulting and Construction Supervisory Joint stock Company (SVG Engineering)
- Year of implementation: 2024


SVG Engineering supervised the construction, completion acceptance of the Tongwei factory phase 1 put into use

MISSION OF CONSTRUCTION SUPERVISION AND COMPLETE ACCEPTANCE OF TONGWEI FACTORY PROJECT PHASE 1 IN VIETNAM

- Completing the factory building is a task that must be carried out to make the factory building meet the goals of comfort and aesthetics.

- Completing factory works includes many different works such as plastering or plastering structural coating surfaces, smoothing or paving floors, wall cladding, painting or whitewashing walls and ceilings, cutting and installing glass, and polishing Wooden and metal furniture, interspersing joints and joints, spreading carpet coverings... Completing the factory project is the final step of the construction work, so the aesthetic quality as well as the comfort of the building is guaranteed. The factory construction will be pretty much determined by the quality of the finishing work. Like the process of supervision and acceptance of other construction works, the supervision and acceptance of factory completion work needs to be supervised as a finishing step, but it is necessary to link the finishing stage with all stages in the process. Factory construction product creation process.

- The process of supervising factory buildings requires attention to the following steps:

  • Check the materials used in each finishing work of the factory, compare the technical requirements in the bidding documents with the catalogs of supplied materials, compare the materials introduced in the catalogs with used artifacts. If you see any differences or have any doubts about the quality, you need an explanation from the construction contractor and material supplier.
  • Materials that will be used in completing the factory project need to have a clear origin regarding the manufacturer, seller and technical specifications clearly stated in the catalogs. The quality of materials must be in accordance with the catalogs and the catalogues must be in accordance with the requirements stated in the tender documents.
  • Materials used to complete factory projects need to be transported from the source of supply to the construction site in accordance with shipping and handling instructions. The process of transporting materials must not cause the product to change its properties, shape or size. When loading and unloading, it must be gentle and ensure that the materials are not subject to mechanical impact or changes in chemical or biological properties compared to the quality criteria agreed upon when negotiating the sales contract.
  • Materials that need to be stored in accordance with the technical requirements stated in the bidding documents and the storage regulations in the catalogs. Do not mix materials, causing changes in the properties of materials during preservation and storage.
  • It is necessary to check the quality of the work stages to create the foundation structure before completion. Fully prepare the ground conditions to receive the finishing stages. The surface that receives the proposed finishing work, such as the glued surface, must be rough enough to adhere tightly, ensuring flatness and no roughness that reduces the quality of the finished surface, for example.
  • The work that must be carried out before finishing must be completed so that after receiving the finishing work, it is not possible to chisel or damage the finishing layers. These tasks are very diverse and easy to forget, so the quality supervision consulting engineer needs to ask the contractor to prepare construction measures to complete the factory project, paying attention to the preparation of finishing stages, the finishing process, and the criteria that must be met, testing methods to identify finished quality, testing tools as well as testing procedures.

Basic steps to note that can be suggested before completing construction:

+ Seal the gaps created by the architectural design in structures with appropriate materials and meet the requirements for tightness and tightness of stuffing and bonding materials.

+ Gaps between components such as gaps between house structures and door frames, moisture resistance, rust resistance, rot resistance, and termite resistance of metal, wood, and plastic materials, and the firm attachment of the mold to the building.

+ Check waterproofing layers before paving, cladding or creating coatings.

+ Check the completeness of pipes that must be placed underground such as electrical conduits, water pipes, pipes containing specialized wires, cavities that need to be left for future work, and pre-placed details for future work.

  • It is necessary to pay attention to labor safety requirements in the completion of factory projects such as scaffolding measures, working floors, fire and explosion prevention measures, anti-toxic measures, and chemical protection measures.
  • Before completing each stage of the factory project, the contractor must also establish construction measures and quality supervision consultants. Besides, the investor must carefully review and submit them to the project manager for approval before construction. (Do not proceed with completion without approval of factory completion construction measures).

​- Factory completion work needs to be linked to ensuring labor safety, fire prevention and other State regulations such as environmental protection, color harmony as well as other traditional elements, culture, ethnicity. The construction process does not cause inconvenience or unsafety to neighboring houses as well as ensuring it does not emit unpleasant vapors, smoke, dust, or dirty water to the environment and construction area.

- Compliance with the regulations of the bidding documents and standards for construction and completion of factory works must also comply with other standards related to the construction and completion of factory works.

IMAGES OF CONSTRUCTION SUPERVISION AND COMPLETE ACCEPTANCE OF TONGWEI FACTORY PROJECT PHASE 1 IN VIETNAM

COST OF FACTORY/WORKSHOP CONSTRUCTION SUPERVISION IN VIETNAM

Please immediately contact Hotline: 0902.593.686 (Mr. Thang) & Email: svg.engineer@gmail.com for support and advice on issues related to Factory/Workshop/Plant construction supervision in Viet Nam ... Best regards! 


VietNam construction consulting - Mr. Thang 0902.593.686

CONTACT US:

SAO VIET DESIGN CONSULTING AND CONSTRUCTION SUPERVISORY JOINT STOCK COMPANY

🏢 Hai Phong Office :

SVG Building, Bui Vien Street, Le Chan District
☎ Tel: (0225) 3.747.819
📞 Hotline: 0902.593.686
📧 Email: svg.engineer@gmail.com & svg.group2005@gmail.com

🌎 VietNam Website: giamsatcongtrinh.com 
🌎 English Website: en.giamsatcongtrinh.com
🌎 China Website: cn.giamsatcongtrinh.com

 Youtube Channel: https://www.youtube.com/@svgengineering

🏢 Representative offices:

1, Ha Noi: No. 9, Alley 81 Hoang Cau Street, Dong Da District
2, Ho Chi Minh: 2/1C Cao Thang Street, 05 Ward, 3 District