AUTHOR SUPERVISION OF WOLONG FACTORY CONSTRUCTION DESIGN CONSULTANCY IN AN DUONG INDUSTRIAL PARK IN HAI PHONG

11/9/2020 | 864 views

The construction design contractor of the industrial park factory project not only ensures the quality of the design documents but also needs to strictly carry out the author's supervision of the unit implementing the design. Sao Viet Construction Inspection and Design Consulting Joint Stock Company (SVG Engineering) has enough experience, capacity, bravery and confidence to effectively supervise design consultants. .

Mr. Tu Peng Yuan, representative of Wolong Vietnam Electric and Gas Co., Ltd., highly appreciated SVG's professional and dedicated working style through supervision and author supervision of the design consultancy for the construction of gas power plants. Wolong Industrial Park An Duong Hai Phong. Very charming with industrial park factory construction projects. Owners are Chinese enterprises, SVG Enigneering architects always promote their outstanding strengths through each design and construction contract. project acceptance.

AUTHOR SUPERVISION OF CONSTRUCTION DESIGN CONSULTANCY IN INDUSTRIAL PARK

The design unit's supervision during the construction process is understood as performing the work including activities such as checking, handling, explaining problems, changes or arising in the construction process. construction process.

The author's supervision of the design contractor during the construction process helps to ensure the construction, installation, adjustment of materials, information technology equipment, commercial or development software, upgrade, edit internal software, database in accordance with construction design and ensure copyright of individuals, organizations, construction design consultants.

AUTHOR SUPERVISION OF WOLONG FACTORY CONSTRUCTION DESIGN CONSULTANCY IN AN DUONG INDUSTRIAL PARK IN HAI PHONG

Sao Viet Construction Inspection and Design Consultancy Joint Stock Company (SVG Engineering) is proud when the efforts during 15 years of building the "brand" have paid off properly. Up to the present time, we confidently affirm the prestige and professionalism of the No. 1 industrial park project design consultancy unit in Hai Phong. And most importantly, we build trust with customers who are business owners, domestic and foreign investors with the design bidding packages of large-scale factory, factory, and industrial park projects. . Not only affirming to customers the professionalism and creativity in each design drawing, but also showing the dedication and responsibility to the supervision and author supervision of the design consultant. factory construction.

After completing and handing over the complete design and construction documents of Wolong gas power plant, An Duong Industrial Park, Hai Phong. Architect Sao Viet (SVG Engineering) continues to perform the role of supervising author and design consultant. The architects have fulfilled the responsibility of the unit directly developing the construction planning design, project planning and acceptance of the construction design. Author supervision is a difficult job that requires skills. and experience. Sao Viet has excellently demonstrated its ability and practical experience through the author supervision of the design consultant for the construction of Wolong Vietnam gas power plant owned by Joint Venture Investment Co., Ltd. Tham Viet.

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Specifically, the task of SVG Engineering in supervising the author of the design of Wolong factory construction, An Duong Industrial Park, Hai Phong:

– Explain and clarify construction design documents at the request of the investor, construction contractor and construction supervision contractor of Wolong gas power plant.

– When required to coordinate with the investor in solving problems, when there is a design problem during the construction period, adjust the design in accordance with the actual construction of the work, handle design inconsistencies.

- When detecting construction that is not compared with the approved design of the construction contractor, promptly notify the investor and propose a timely handling plan.

– Participating in the construction acceptance process, completed items of the factory construction project at the request of the investor.

– When completing the supervision, record all information in the construction log book or in writing.

INFORMATION OF AUTHOR SUPERVISION OF WOLONG FACTORY CONSTRUCTION DESIGN CONSULTANCY IN AN DUONG INDUSTRIAL PARK IN HAI PHONG

Investor: Tham Viet Investment Co., Ltd

Address: An Duong Industrial Park (An Duong District - Hai Phong City)

Project: Construction of Wolong gas power plant

Duties: Design Consultant and Author Supervision of Construction Design Consultant

Executing unit: Sao Viet Construction Inspection and Design Consultancy Joint Stock Company

Year of implementation: 2020


CONTENT OF AUTHOR SUPERVISION OF WOLONG FACTORY CONSTRUCTION DESIGN CONSULTANCY IN AN DUONG INDUSTRIAL PARK IN HAI PHONG

With many years of experience working with foreign partners, implementing a series of design plans for the construction of Chinese enterprise industrial park factory projects, Sao Viet is always proactive in work and committed to comply with the correct content according to the most standard process. Author supervision of construction design consultants is the task of SVG architects after handing over the project design documents to complete the acceptance work. A big project like the construction of Wolong gas power plant owned by Tham Viet Investment Co., Ltd. - a close partner of Sao Viet, of course, the author's supervision work. taken more seriously.

Below, we send you the content of the author's supervisory work of the design consultant for the construction of Wolong gas power plant, An Duong Industrial Park, Hai Phong:

– The construction contractor conducts the pre-acceptance test of the work before the request of the investor for acceptance. After the acceptance process is over, problems arise and the transfer of another contractor should be confirmed by the new contractor and re-tested when necessary.

– When there is a written request for acceptance of the construction contractor, the investor must be responsible for organizing the acceptance of the construction work in a timely manner. The construction acceptance process is divided into stages:

a. Conduct acceptance test for each part of construction work during the construction process of Wolong Vietnam gas power plant:

b. Pre-acceptance test of construction parts, construction phase of Wolong Vietnam gas power plant:

c. Conduct acceptance test when the work item is completed and the construction work is put into use.

– When the investor has completed the acceptance test, the new works are allowed to come into use.

– Written acceptance in two languages ​​is required, Vietnamese and Chinese because the business owner is Chinese

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Giam sat tac gia cua tu van thiet ke cong trinh xay dung nha may dien khi Wolong khu cong nghiep An Duong Hai Phong

Author supervision of Wolong factory construction design consultancy in An Duong industrial park in Hai Phong

Monitoring the copyright of the construction design contractor is an important and very important job. It should be carried out by an experienced unit in the field of construction quality supervision. Please give that task to Sao Viet (SVG Engineering), our customers will receive absolute peace of mind. Because of us, experienced, capable and responsible architects will ensure the quality of construction design, construction, efficiency and sustainability. The work of implementation, supervision of the design author is taken place seriously and in accordance with the process and requirements in accordance with the law.

CONTACT INFORMATION: 

SAO VIET DESIGN CONSULTING AND CONSTRUCTION SUPERVISORY JOINT STOCK COMPANY

Hai Phong Office: 

SVG Building - Bui Vien Street - Le Chan District - Hai Phong City 

Tel: (0225) 3.747.819

Website: giamsatcongtrinh.com & en.giamsatcongtrinh.com

Hotline: 0902.593.686 - 0936.547.819

Email: svg.group2005@gmail.com & svg.engineer@gmail.com

Branch office: 

1, Ha Noi Branch Office: No. 9, Alley 81 Hoang Cau Street, Dong Da District, Hanoi Capital

2, Ho Chi Minh Branch Office: 2/1C Cao Thang Street, 05 Ward, 3 District, Ho Chi Minh City